Cupar to Guardbridge 33kV Cable Installation

Call us on

Powering your community

Information about improvements to the electricity network

SP Energy Networks is undertaking work to upgrade our electricity infrastructure in your area, and as part of that, we are about to carry out significant works from Cupar Grid supply point, through the town, along the A91, through Dairsie and onto Guardbridge – see attached map.

We have worked closely with the local authority in planning this project to minimise disruption to the local community where possible.

Traffic restriction orders will be in place during the works, and we kindly ask you to follow any instructions. We apologise for any inconvenience caused and will make every effort to minimise impact to the community while we carry out reinforcements to the local network.​

The main bulk of the work will take place:​

From the 26th of September 2024 until August 2025

For further information and what to expect download the customer communications letter

Download

For emergencies call Walker & Watts on

+44 800 047 2624

For updates email Walker & Watts on

cupar@walkerwatts.co.uk

Video Progress - 10 December 2024

The video shows the progress of the works and the types of activities taking place for works

Below is a summary of the works that will take place and their percentages complete

Please note that the dates below are indicative to the programme, however, if there are challenges with conditions on the routes, the dates may be subject to change.

Moathill Road

Total Length 767m

Completion: 59%

100%

Moathill Road Phase 1 - 403m


Start                        End

06/10/2024      13/10/2024

100%

Moathill Road Phase 2 - Lady Wynd & Northbound - 10m


Start                        End

26/02/2025       01/03/2025

10%

Moathill Road Phase 3 - 354m


Start                        End

31/03/2025      11/05/2025

East Burnside to A91

Total Length 5600m

Completion: 43%

0%

East Burnside - 310m


Start                        End

14/08/2025      02/09/2025

0%

East Road - 876m


Start                        End

24/06/2025      08/08/2025

0%

East Bridge - 120m


Start                        End

06/08/2025       23/08/2025

10%

A91 - East Rd Roundabout to Cottage Bank - 880m


Start                        End

22/03/2025       07/05/2025

0%

A91 - Mainstreet Dairsie to Dairsie RA - 344m


Start                        End

08/05/2025       27/05/2025

0%

Mainstreet Dairsie - 655m


Start                        End

19/05/2025       03/07/2025

100%

A91- Acess Road to FoodHall - 1000m


Start                        End

08/10/2024       26/11/2024

100%

A91 - Cottage Bank to Foodhall Farm - 1400m


Start                        End

25/11/2024       21/03/2025



Statheden Park to Drum Rd Cupar Muir - Westfield Ave Jct


Total Length 1000m



Completion: 100%

100%

Westfield Road - 843m


Start                        End

15/11/2024                  16/02/2025          

100%

Drum Rd Cupar Muir to Westfield Rd - 53m


Start                        End

      21/03/2025          30/03/2025                     

100%

Statheden Park to Drum Rd Cupar Muir - 20m


Start                        End

      28/03/2025          05/05/2025       

A91 Roundabout A914

to Main Street


Total Length 4500m



Completion: 31%

100%

Main Street Guardbridge- 843m


Start                        End

          22/10/2024                  07/03/2025         

100%

Guardbridge Roundabout - 20m


Start                        End

      09/02/2025          07/03/2025                     

100%

 Cupar Road - 257m


Start                        End

    10/02/2025                  25/03/2025     

70%

U118 Jc to Cupar Road Guardbridge - 240m


Start                        End

          25/03/2025                  15/05/2025         

0%

U118 JC to Cupar Road Guardbridge 1236m


Start                        End

    16/04/2025                  02/06/2025                   

0%

Clayton Caravan Park to U118Jc - 570m


Start                        End

        31/05/2025        23/06/2025                     

14%

A91 - Dairsie RA to Clayton Caravan Park - 125m


Start                        End

          24/06/2025                  28/07/2025         

0%

A91 - Dairsie RA to Clayton Caravan Park - 560m


Start                        End

      15/07/2025          28/07/2025                     


Westfield Avenue


Total Length 240m



Completion: 100%

100%

Westfield Ave Phase 1 - 108m


Start                        End

                       07/11/2024             16/11/2024                    

100%

Westfield Avenue Phase 2 - 138m


Start                        End

                    16/04/2025         02/05/2025