Cupar to Guardbridge 33kV Cable Installation

Call us on

Powering your community

Information about improvements to the electricity network

SP Energy Networks is undertaking work to upgrade our electricity infrastructure in your area, and as part of that, we are about to carry out significant works from Cupar Grid supply point, through the town, along the A91, through Dairsie and onto Guardbridge – see attached map.

We have worked closely with the local authority in planning this project to minimise disruption to the local community where possible.

Traffic restriction orders will be in place during the works, and we kindly ask you to follow any instructions. We apologise for any inconvenience caused and will make every effort to minimise impact to the community while we carry out reinforcements to the local network.​

The main bulk of the work will take place:​

From the 26th of September 2024 until August 2025

For further information and what to expect download the customer communications letter

Download

For emergencies call Walker & Watts on

+44 800 047 2624

For updates email Walker & Watts on

cupar@walkerwatts.co.uk

Video Progress - 10 December 2024

The video shows the progress of the works and the types of activities taking place for works

Below is a summary of the works that will take place and their percentages complete

Please note that the dates below are indicative to the programme, however, if there are challenges with conditions on the routes, the dates may be subject to change.

Moathill Road

Total Length 767m

Completion: 53%

100%

Moathill Road Phase 1 - 403m


Start                        End

06/10/2024      13/10/2024

0%

Moathill Road Phase 2 - Lady Wynd & Northbound - 10m


Start                        End

26/02/2025       01/03/2025

0%

Moathill Road Phase 3 - 354m


Start                        End

27/02/2025      23/03/2025

East Burnside to A91

Total Length 5600m

Completion: 33%

0%

East Burnside - 310m


Start                        End

31/01/2025      27/02/2025

0%

East Road - 876m


Start                        End

21/02/2025      10/04/2025

67%

East Bridge - 120m


Start                        End

04/04/2025       27/04/2025

0%

A91 - East Rd Roundabout to Cottage Bank - 880m


Start                        End

16/02/2025       17/03/2025

0%

A91 - Mainstreet Dairsie to Dairsie RA - 344m


Start                        End

15/03/2025       30/03/2025

0%

Mainstreet Dairsie - 655m


Start                        End

31/03/2025       12/05/2025

100%

A91- Acess Road to FoodHall - 1000m


Start                        End

08/10/2024       26/11/2024

61%

A91 - Cottage Bank to Todhall Farm - 1400m


Start                        End

25/11/2024       17/02/2025



Statheden Park to Drum Rd Cupar Muir - Westfield Ave Jct


Total Length 1000m



Completion: 74%

77%

Westfield Road - 843m


Start                        End

15/11/2024                  16/02/2025          

0%

Drum Rd Cupar Muir to Westfield Rd - 53m


Start                        End

      21/03/2025          30/03/2025                     

0%

Statheden Park to Drum Rd Cupar Muir - 20m


Start                        End

      28/03/2025          05/05/2025       

A91 Roundabout A914

to Main Street


Total Length 4500m



Completion: 7%

77%

Main Street Guardbridge- 843m


Start                        End

          22/10/2024                  16/02/2025         

0%

Guardbridge - 20m


Start                        End

      09/02/2025          12/02/2025                     

0%

 Cupar Road - 257m


Start                        End

    10/02/2025                  01/03/2025     

0%

U118 Jc to Cupar Road Guardbridge - 240m


Start                        End

          27/02/2025                  14/03/2025         

0%

U118 JC to Cupar Road Guardbridge 1236m


Start                        End

    12/03/2025                  01/05/2025                   

0%

Clayton Caravan Park to U118Jc - 570m


Start                        End

        20/04/2025        18/05/2025                     

0%

A91 - Dairsie RA to Clayton Caravan Park - 125m


Start                        End

          16/05/2025                  28/05/2025         

0%

A91 - Dairsie RA to Clayton Caravan Park - 560m


Start                        End

      25/05/2025          18/06/2025                     


Westfield Avenue


Total Length 240m



Completion: 45%

100%

Westfield Ave Phase 1 - 108m


Start                        End

                       07/11/2024             16/11/2024                    

0%

Westfield Avenue Phase 2 - 138m


Start                        End

                    14/02/2025         28/02/2025                   



Share by: